Appendix A  

 

Proposed Schools Condition Capital Programme 2024/25

Amount (£)

 

Potential Capital Funding Available:

 

Capital Planned Maintenance Programme 23/24 carry forward

254,137

General compliance/H&S 23/24 carry forward

120,896

Accessibility Schemes 23/24 carry forward

34,488

Estimated contribution from School’s Devolved Formula Capital (DFC) in 24/25

150,000

General contingency 23/24 carry forward and unallocated

2,028,950

Schools Condition Allocation 24/25

5,883,316

Total Potential Capital Funding Available

8,471,787

 

Capital Maintenance and Compliance/Regulatory Requirements:

 

General Compliance and Health & Safety

200,000

Capital Planned Maintenance Programme (£150k DFC contributions + £6.21m)

6,509,191

Condition Survey & Asbestos Reinspection’s – internal fee

245,000

Accessibility Schemes

200,000

 

Total Capital Maintenance and Compliance/Regulatory Requirements

7,154,191

 

Proposed Capital Investment – Strategic Priorities:

 

Works arising from the amalgamation of Caedmon College / Eskdale

250,000

 

 

Total Proposed Capital Investment - Strategic Priorities

250,000

 

Strategic Support for Capital Projects – Property Service

67,596

 

Total Proposed Investment

7,471,787

General Contingency / Unallocated

1,000,000